Composite Deck on a Steep Wooded Lot in Maryville, TN

164 sq ft of composite deck and boardwalk · helical piers driven 24 ft and 14 ft · composite stairs down the slope with landings · black aluminum railing throughout.

Finished composite deck with black aluminum railing on a wooded lot in Maryville, TN
Google Guaranteed badge
NADRA member badge
Deckorators Certified Pro badge
Envision Outdoor Living Products logo
Home Builders Association of Greater Knoxville member logo
National Association of Home Builders member logo
Deckorators Certified Elite badge
Loudon County Chamber of Commerce logo
Old wood stairs and railing along a steep grassy slope

Part One : An Old Deck at the Foot of a Maryville Hillside

The first soil test on this lot, on July 17, found soft ground all the way down to 36 in. Every footing on the new deck was chosen with that result in hand.

The old deck sat at the bottom of a wooded slope behind the house. A wood boardwalk ran down to it from the concrete patio, and a long wood stairway climbed the hill back to the house.

We photographed the layout on May 21, and on the July 1 visit the timber steps at the deck were breaking apart and one post base was badly worn.

The homeowner wanted the new upper deck to meet the existing patio. At that same meeting we raised two questions: how much dirt work it would take, and whether the hillside soil would hold new posts.

What We Found

Worn post base and rotting timber steps at the old deck
Underside of the old wood deck and its posts on sloped ground
Old wood deck on a wooded lot in Maryville, TN, before the replacement

Part Two : Soil Testing, Helical Piers and a Price That Held

Underside of the old wood deck and its posts on sloped ground

Testing Before Digging

The soil test came back soft on July 17, so we brought in a soil engineer. On July 28 the engineer approved a poured footing for the middle of the stairs and helical piers for the top.
Old wood deck on a wooded lot in Maryville, TN, before the replacement

Holding the Price

The engineering and the piers added cost, so we made the lower deck a little smaller to cover it. The reworked August 17 contract came to the same total as the one signed in May.
Helical pier on site before installation for the new deck footings

Footings and Framing

Helical piers where the engineer placed them, plus 11 poured footings at 20 by 20 by 12 in, carry a treated 2×10 frame with joists 12 in apart.
Composite stair treads with black aluminum railing

Decking and Boardwalk

164 sq ft of composite across the deck and the boardwalk, with border boards and an inlay. The fascia and skirting are composite as well.
New deck stairs and landing being built on a wooded slope

Stairs and Railing

Composite stairs run down the slope with 4 by 4 ft landings between flights and end on a concrete pad. Black aluminum railing runs about 64 ft along the deck and boardwalk and 22 ft on the stairs.
Ground cleared on the slope for the new stairway

Permits and Engineer's Letters

The paperwork included the City of Maryville permit, a deck engineer’s letter and a stamped letter from the helical pier engineer. On August 27 the plans gained one more set of steps.

Part Three : Piers in September, Finished by Mid-October

Date What Happened
Sept 14 Slope cleared and marked for the stairway. Helical piers driven, one to 24 ft and one to 14 ft, each until it reached the engineer's required load.
Sept 21 to 28 A machine delay and backordered fascia pushed the start back a couple of days. By Sept 28 two screw piles sat under the stair landing, and the stairs and landings were up with railing.
Oct 5 to 7 Footing inspection record filed Oct 5. The crew was back Oct 7, with the top flight to the house still in open framing.
Oct 14 to 19 Job finished Oct 14 per the crew log. Completion checklist signed Oct 15, and the decking and railing warranties registered Oct 19.
The piers went in on September 14 and the crew log closed the job on October 14, one month later.
New composite stairway being built up a steep slope

Hillside Stairs and Deck, Then and Now

The gray deck at the bottom of the hill is now 164 sq ft of composite on helical piers, with composite stairs and black railing climbing the slope in short flights. For a flat-lot tear-out, see the deck replacement in three days in Knoxville.

Before After Old wood deck on a wooded lot in Maryville, TN, before the replacementFinished composite deck with black aluminum railing on a wooded lot in Maryville, TN
Before After Old wood stairs and railing along a steep grassy slopeFinished composite deck stairs with black aluminum railing
What the hillside job covered:
Helical pier on site before installation for the new deck footings

Helical Piers

A steel shaft with screw plates, turned into the ground until the soil pushes back hard enough to carry the load. One pier went 24 ft and another 14 ft for that reason. Our guide to East Tennessee clay soil compares piers with poured footings.
Finished composite deck with black aluminum railing on a wooded lot in Maryville, TN

Deck and Boardwalk Boards

164 sq ft under the tree canopy, bordered and inlaid over a 2×10 frame.
Finished composite deck stairs with black aluminum railing

Westbury Black Aluminum Railing

Black posts and balusters along the deck, the boardwalk and the stairs. The boxes arrived on September 28.
Lower landing and composite stairs with black aluminum railing in Maryville, TN

Composite Stairs and Landings

Landings split the climb into short flights, and the bottom flight ends on a poured concrete pad. More on how we build deck steps.

Materials and Finishes

Composite Deck Builder, Maryville, TN: Building Under Trees

A deck under a tree canopy stays damp longer than one in open sun, because leaves land on it and the shade holds the moisture, and an East Tennessee summer adds humidity on top. That is how the old wood deck and stairs on this lot went gray and the timber steps came apart.

Composite boards take on far less water than pressure-treated wood, so the decking, the stair treads and the skirting here are all composite, and the pressure-treated 2×10 frame sits above grade on footings and piers where it stays drier.

The other half of deck building in Blount County is the site conditions: a slope, soft ground, and a stairway that has to be broken into flights with landings, and on this job that meant a soil engineer, helical piers and a multi-level layout that climbs the hill in short runs.

We serve Maryville from Knoxville, every footing gets sized to what the ground will hold, and the decking and railing warranties were registered with the manufacturers at closeout.

Why did this Maryville deck need helical piers?

The July 17 soil test found soft ground to 36 in, so a soil engineer placed helical piers at the top of the stairway and a poured footing in the middle, and each pier was driven until the ground pushed back hard enough to carry the load.

How long did the hillside deck take to build?

The piers went in September 14 and the crew log closed the job October 14, with a machine delay and backordered fascia inside that month.

What does a composite deck on a slope cost?

This one was $35,058, the same total as the May contract, because a slightly smaller lower deck paid for the soil engineer and the piers.

This Hillside Deck and Stairway Was $35,058

The total is the same as the contract signed in May. A smaller lower deck paid for the soil engineer and the piers, and the rest of the plan stayed as drawn. Financing is available.

960+

decks built & repaired

600+

clients served

115+

5-star reviews

60+

years of combined experience

Meet the Owner

Riverview Decks is run by its president, Nate Burket, out of Knoxville. Every new composite deck the crew builds carries a transferable double-lifetime workmanship warranty with no expiration, and the company is a NADRA member, Deckorators PRO Certified Elite, and licensed, bonded, and insured.

What Your Neighbors Say

Heather M. Burke

Rated 5 out of 5

We love our deck. More than we thought we would. Nate was great at helping get the design right and Emmanuel made sure it was build right and we were happy

… or read more on

Joe Bucci​

Rated 5 out of 5

I found Riverview Decks to be extremely easy to work with. They recently completed a deck and stair project for us. We gave them a mostly baked idea of what we wanted and they came up with a final design we just love that worked for our budget. Easily my favorite contractor I’ve worked with. Couldn’t recommend them enough.

… or read more on
blank

Greg Berney

Rated 5 out of 5

Nate and the entire team at Riverview Decks do an incredible job. Highly professional, fair pricing, and great service. They show up when they say the will, provide high quality in their work, and are always responsive. I highly recommend them for your deck work.

… or read more on

Find Out What Your Hillside Will Hold Before You Plan a Deck on It

If your yard drops away from the house, the soil under it decides what the footings will be, and the footings decide the price, so we test the ground before we quote. You can also look at more finished deck projects in Knoxville or read our guide to clay soil and deck foundations. Call (865) 801-4545 or fill out the form.

Nate Burket, owner of Riverview Decks, deck builder in Knoxville, Tennessee
Hi, I’m Nate, the owner of Riverview Decks. Please take 2 minutes to fill out the form so we get the info we need to call you back. Me or someone from my office will reach back with a phone call to discuss your new decking project. Looking forward to hearing from you!